TTS needed to find a solution for a dangerous curve that required a new crash barrier. Arup developed the system and loading and Geomarine developed the design to handle the loads.
This involved the formation of Grundo piles with Ischebeck Titan anchors to stop the over turning moment. This was cast into a base that had a specialist Tertu barrier (a metal barrier with wood cladding). This work was completed with ancillary works such as some kerbing and draining modifications.
To downloand a pdf of the project details, please click on the link below:-
TTS
6 weeks
Arup/Geomarine/T&G